Until May 08, suddenly client want it back.
And they want it urgently, force us to deliver the crane by End July. Shall i use the word force?? Contractually we suppose had completed it by year 2006, but we did not...
During the in between period, drwgs revised, the design improved, but all newly added componenets not purchase?! And they are all long lead time item.
We want to rush the crane assy, but, unfortunately, almost all critical components (which purchased) had MIA ( Missing In Action), no matter the size is big or small...That is not funny...i am sure.. repurchase need a mising report as supporting doc, but no one willing to issue that report, coz have to see our GM and explain to him about the cost of repurchase... "Cost" a word where all GM very sensitive to.
Drwgs error is also one of the big contributor to the delay, eg: dimension not match lah, pin longer then hole lah, hole bigger dia. then pin lah, components blocking each other lah, no current supply lah, cable size wrong lah, Part number wrong lah...
Plus parts damaged lah, parts unable to source lah, buyer/PC/Production overlooked lah, parts missing lah..a lot and a lot..
All these issues i digested and resolved one by one, my untiring effort.. i am pround of myself, sometime...
Next Monday will meet with client, then i had prepareed myself "bi tan yi". God will bless me...
Gambateh ne!!
ReplyDeletei know u can!
In fact,this is a great shit that you take la,
ReplyDeletei believe this is a test from God,
God wan you to learn something from this "Delayed Crane"...
For your info,
i'm the person in charge in Mast,hope it's no problem when the T & C going la.
hihi...
You dare to comment, your know there is a fabrication error in the Mast? Port side hole you did it at Starboard side!!
ReplyDeleteBut ok lah, i settled it edy.
***ANGRY****